Processing times vary considerably. Minor variations and simple domestic bespoke permit applications typically take four months. Complex bespoke and standard rules permits can take eight to twelve months. It is important to factor these timescales into your project programme and not to proceed with installation before the permit is in place where one is required.
Processing times vary considerably. Minor variations and simple domestic bespoke permit applications typically take four months. Complex bespoke and standard rules permits can take eight to twelve months. It is important to factor these timescales into your project programme and not to proceed with installation before the permit is in place where one is required.