Insurance Instruction Resolved in Three Days – Bespoke EA Permit for a Dry Ditch

Appley Croft Barn’s failing septic tank triggered an insurance instruction. Clay soils ruled out a drainage field. WCI Water & Wastewater Engineers obtained a bespoke EA permit and completed the full installation in three days.

Somerset

Summary

  • 3 days - full installation from start to finish
  • Bespoke EA permit secured for a seasonally dry ditch discharge
  • Installation commenced ahead of permit issue - agreed with the local EA officer

Project in numbers

3 days

Full installation

Overview

Appley Croft Barn’s failing septic tank triggered an insurance instruction to WCI. Clay soils ruled out any drainage field, and a seasonally dry ditch was the only discharge option – requiring a bespoke permit rather than General Binding Rules registration. WCI delivered the whole solution in three days.

The Challenge

Clay soils prevented any drainage field. A bespoke permit was needed for the seasonal ditch discharge, but the insurance instruction meant the work needed to start promptly.

The WCI Solution

WCI discussed the discharge route with the local EA officer and agreed to commence installation ahead of the formal permit application. A Building Notice was submitted and the new STP was installed in three days.

The Outcome

Appley Croft Barn fully compliant within three days, resolving the insurance requirement.

To discuss your installation or groundworks project, contact WCI today.

Talk to our team of experts for assistance on your project

Naomi Taylor
WCI Group Director
01984 623 404
Speak to the experts

Contact one of our specialist across our four divisions

Get in Touch