A Problem-Solving Installation – Excavator Over the Wall, Through the Piggery

Down Farm had been unsellable for two years because of its failing drainage. WCI Water & Wastewater Engineers solved it – lifting a small excavator over a garden wall and routing the rising main through a historic piggery yard.

Devon

Summary

  • 2 years the property had been unsellable - resolved by WCI
  • Small excavator lifted over the garden wall by long-boom hiab from the road
  • Rising main routed through a working piggery yard to reach the STP

Project in numbers

2 years

Property had been unsellable - resolved by WCI

Overview

Down Farm had been unsellable for two years because of its failing drainage. WCI Water & Wastewater Engineers solved it – with an installation that required lifting a small excavator over a garden wall and routing the rising main through a historic piggery yard with a slurry pit in the middle.

The Challenge

The rear garden was inaccessible except by lifting machinery over a garage from the road. The only viable route for the rising main passed directly through the working piggery yard.

The WCI Solution

A WPL DMS2 STP with separate pump chamber was installed under the tarmac driveway. A small excavator was lifted over the garage wall by hiab from the road, enabling the soakaway to be installed in the otherwise inaccessible garden. The rising main was routed through the piggery, under a garden wall and to the STP.

The Outcome

Down Farm was saleable after two years. The system is compliant with current Building Control and EA regulations.

To discuss your installation or groundworks project, contact WCI today.

Talk to our team of experts for assistance on your project

Naomi Taylor
WCI Group Director
01984 623 404
Speak to the experts

Contact one of our specialist across our four divisions

Get in Touch